Connecticut General Statutes § 49-41c

State contractor to make payment to subcontractor within thirty days.

Title 49 · Chapter 847 · General Statutes of Connecticut, revised to January 1, 2025

Any person contracting with the state shall make payment to any subcontractor employed by such contractor within thirty days of payment by the state to the contractor for any work performed or, in the case of any contract entered into on or after October 1, 1986, for materials furnished by such subcontractor, provided such contractor may withhold such payment if such contractor has a bona fide reason for such withholding and if such contractor notifies the affected subcontractor, in writing, of his reasons for withholding such payment and provides the state board, commission, department, office, institution, council or other agency through which such contractor had made the contract, with a copy of the notice, within such thirty-day period. (P.A. 83-552, S. 1; P.A. 86-12, S. 2.) History: P.A. 86-12 made section applicable to payment for materials as well as labor. cga.ct.gov

The text above is reproduced word for word from its official source. General information only — not legal advice.

← § 49-41bTitle 49 — all sections§ 49-42 →
Share