Connecticut General Statutes § 16-262k
Interconnection of public water supply systems to relieve site-specific water shortages.
Title 16 · Chapter 283 · General Statutes of Connecticut, revised to January 1, 2025
The Public Utilities Regulatory Authority may require any water company as defined in section 16-1 to connect its public water supply system with that of another water company or municipal utility if it finds that such a connection would be an effective means of relieving site-specific water shortages.
(P.A. 81-358, S. 3; P.A. 11-80, S. 1.)
History: Pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011.