Changing electric suppliers.

Title 16 · Chapter 283 · General Statutes of Connecticut, revised to January 1, 2025

A customer may change his electric supplier, as defined in section 16-1, at any time. The electric distribution company, as defined in said section 16-1, and electric supplier may each charge a reasonable fee, as approved by the Public Utilities Regulatory Authority, to make a change in the customer's supplier to reflect the actual cost to read the customer's meter and make changes in its billing records, except that every customer may seek a change in his electric supplier without charge once in any twelve-month period if the change occurs at the end of the customer's regularly scheduled meter reading and billing cycle. (P.A. 98-28, S. 28, 117; P.A. 11-80, S. 1.) History: P.A. 98-28 effective July 1, 1998; pursuant to P.A. 11-80, “Department of Public Utility Control” was changed editorially by the Revisors to “Public Utilities Regulatory Authority”, effective July 1, 2011. cga.ct.gov

The text above is reproduced word for word from its official source. General information only — not legal advice.

← § 16-245pTitle 16 — all sections§ 16-245r →
Share